Speed of A is 50% more than B and B alone require 20 days to do certain amount of work so how much time A and B together require
Answers
Answered by
0
Answer:
A and complete work together in 16 days.
Step-by-step explanation:
Given ,
A work 50% faster than B
B complete work in 20 days.
Suppose total work is 20.
So
B complete 1 work per day
So A is 50% faster than B
A complete 1.5 work per day.
So A+B = 2.5 work/day
So,
20 works complete in (20/2.5) = 16 Days.