Standard Quantity = 9000 Kgs; Actual Quantity used = 9100 kp. Standard Price = 16 Rs. Per Kg: Actual Price paid=16.2 Rx. Per kg Compute Material Price Variance, Material Usage variance and Material Cost Variance
Answers
Answered by
1
Answer:
answer is 18,132.2 is answerthe question