Math, asked by dassanjib4allp7zdm0, 3 months ago

Sumesh and Soni can complete a work together in 100 days. If Sumesh works four times its capacity and Sony works half of its capacity, the work is completed in 40 days. In how many days can Sumesh and Sony complete the work alone respectively?​

Answers

Answered by harikaran9788
1

Step-by-step explanation:

( su+so)100 = (4su+so/2) 40

5su+5so = 16su+2so/2

10su +10so = 16su+2so

6su = 8so

su/so = 8/6 = 4/3

tw = 700

= 700/4 = 175days✅ sumesh

= 700/3 = 233.33 ✅ soni