Sumesh and Soni can complete a work together in 100 days. If Sumesh works four times its capacity and Sony works half of its capacity, the work is completed in 40 days. In how many days can Sumesh and Sony complete the work alone respectively?
Answers
Answered by
1
Step-by-step explanation:
( su+so)100 = (4su+so/2) 40
5su+5so = 16su+2so/2
10su +10so = 16su+2so
6su = 8so
su/so = 8/6 = 4/3
tw = 700
= 700/4 = 175days✅ sumesh
= 700/3 = 233.33 ✅ soni