Math, asked by gaishwarya2126, 7 hours ago

Sumit can complete 25% of a piece of work in 3 hrs. Anurag and Sumit can complete the whole work in 4 hrs. How much time (in hours) does Anurag require to complete 50% of that work?
2
1
3
6​

Answers

Answered by rowdy2402
0

Answer:

he takes 2 hours to complete

Step-by-step explanation:

Anurag can complete total work in 4

as we halve it we get 2 hours

please mark me as brainlist

Answered by rinayjainsl
0

Answer:

(C)Anurag will take 3 hours to finish 50% of work

Step-by-step explanation:

Given that,

Sumit can complete 25% of a piece of work in 3 hrs.

Let us assume that,the total work that needs to be done is 1 unit.

Therefore,sumit completes \frac{1}{4} units of the work in 3 hours.

Therefore,Work done by sumit in 1 hour is \frac{1}{4\times3} =\frac{1}{12} units

Let us assume that,the work done by Anurag in 1 hour is \frac{1}{x}   units

According to the given problem,Anurag and Sumit can complete the whole work in 4 hours.Hence,mathematically we write it as shown below-

\frac{4}{12} +\frac{4}{x} =1= > \frac{4}{x} =\frac{2}{3} \\= > x=6 hours

It means that anurag can complete the whole work in 6 hours.Hence,to complete 50% of work,anurag will take-

\frac{6}{2} =3 hours

Therefore,Anurag will take 3 hours to finish 50% of work

#SPJ2

Similar questions