Sunil takes 5 days more
ays more than Anil to complete a certain work. 4 days after starting
left the work. The remaining work was done by Sunil in 5 days.
the work, Anil left
many days each will take to complete the work.
Find how many days each
will take to complete the work
Answers
Answered by
0
Step-by-step explanation:
Let x be the no of days taken by anil to complete it
Now, given that
Sunil =x+5
Anil=x
Now from question
4(S+A)+5(s)=1
4(1/x+5 + 1/x) +5/x+5 =1
Solve this to get ur answer....