Sunil takes 5 days more than anil to complete a certain work . 4 days after starting the work ,anil left the work. The remaining work was done by sunil in 5 days. Find how many days each will take to complete the work
Answers
Answered by
7
Answer:
Anil takes 10 days and Sunil takes 15 days.
Step-by-step explanation:
The number of days taken to complete the job ( Anil ) = x
Then,
The number of days taken to complete the job ( Sunil = x + 5
Anil in one day = 1 / x
Sunil in one day = 1 / ( x + 5 )
Working together,
For one day,
1 / x + 1 / ( x + 5 )
2x + 5 / x ( x + 5 )
4 days together and 5 days by sunil,
4 * ( 2x + 5 ) / ( x ( x + 5 ) + 5 * 1 / ( x + 5 ) = 1
Solving for x,
We get,
x = 10
Substituting,
Hence,
Work done by Anil = 10 days
Work done by Sunil = 15 days.
hope this helps you.