Sunil takes 5 days more than Anil to complete a certain work. 4 days after starting
the work, Anil left the work. The remaining work was done by Sunil in 5 days.
Find how many days each will take to complete the work.
Answers
Answered by
1
Answer:
answer is 10 and 15 anil 10 and Sunil 15