Sunil takes 5 days more than Anil to complete a certain work 4 days after starting the work Anil left the work. The remaining work is done by Sunil in 5 days. find how many days each will take to complete the work ​

Answers

Answered by kbalasaheb
76

Anil takes 10 days and Sunil takes 15 days.