Suppose that the time it takes to do a job is inversely proportional to the number of workers. That is, the more workers on the job the less time required to complete the job. Is it takes 2 workers 8 days to finish a job, how long will it take 8 workers?
Answers
Answered by
4
Answer -
Attachments:
Similar questions