suresh and majid can do a piece of work in 12 days.
Suresh after doing
for 16days
majid takes 22 more days to
Complete that work, How many days suresh
take to
to complete the
work
alone.?​

Answers

Answered by swarnabidas
4

Answer:

38 days

please mark me brainliest.. if you wish

Answered by minecraftshreyas
0

38 days