Suresh can do a piece of work in 40 days he works at it for 5 days and leaves then Roshan finishes it in 21 days in how many days will Suresh and Roshan working together do the work
Answers
Answered by
3
Step-by-step explanation:
Given ,
Suresh can complete a work in 40 days. So his one day work is 1/40
Let Roshan can complete the work in x days.
So , one day work of roshan = 1/x
ATQ ,
Work left after Suresh left = 1-1/8 = 7/8
Now ,
21(1/x) = 7/8
(1/x) = 7/(8×21)
1/x = 1/24
x = 24
Their combined one day work = 1/24 +1/40 =8/120 = 2/30 = 1/15
So , they'll together complete the work in 15 days