Suresh can finish a work in 15 hours. Ashutosh can finish the same work alone in 10 hours .if Suresh work alone for 9 hours and leaves .How many hours will be required to complete the work by Ashutosh?
Answers
Answered by
2
i think its the answer
if you like it mark as brainleist and also follow me
if you like it mark as brainleist and also follow me
Attachments:
akchita124pekc5c:
tanx and I'll follow you
Answered by
0
Concept:
Unitary method is a way for solving a particular problem by first calculating the value of a single unit, and then finding the necessary value by multiplying the single unit value.\
Given:
Suresh can finish a work in 15 hours.
Ashutosh can finish the work alone in 10 hours .
Find:
Number of hours required to complete the work by Ashutosh.
Solution:
Suresh's 1 hour's work = 1/ 15 units
Ashutosh's 1 hour's work = 1/ 10 units
Suresh's 9 hours' work
= 9 × 1/ 15 = 3/ 5 units
remaining work = 1 - ( 3/ 5)
= 2/ 5 units
Ashutosh will finish the remaining work in
= (2/ 5) ÷ (1/10)
= 20 ÷ 5 = 4 hours
Therefore, Ashutosh will finish the remaining work in 4 hours.