T. A work could be completed in 100 days.
However, due to absence of 10 workers, it
was completed in 110 days, the original
numbers of workers were​

Answers

Answered by hrn21agmailcom
0

Answer:

110

Step-by-step explanation:

n workers do in one day = 1/100part

(n-10) workers do in one day = 1/110 part

hence 10 workers do in one day = (1/100 ) - (1/110)

= 1/1100 part

means 1100 days taken by 10 workers to finish

then 100 days taken by = 1100*10/100 = 110 workers

hence total workers = 110