t takes 10 people 5 days to complete a piece of work at a factory when working 2 hours a day. Working at the same pace, how many days will it take 2 people to do the same work, if they are working 5 hours a day?

Answers

Answered by rubal95
1
it will take 10 days to complete the task
Answered by Shaizakincsem
1

Thank you for asking this question. Here is your answer:

First we will solve this:

m1×d1×t1 =m2×d2×t2

10×5×2=2×d2×5

10×10=10×d2

d2=100/10

d2=10

Means it will take around 10 days for them to complete it. This is the final answer.

If there is any confusion please leave a comment below.