Takes 6 days less than q to finish the work individually. if p and q working together complete the work in 4 days, then how many days are required by q to complete the work alone ?
Answers
Answered by
1
let p takes x days
so p's work in a day = 1/x
q requires x+6 days
so q's work in a day = 1/x+6
now
1/x + 1/x+6 = 1/4
x+6 + x / x(x+6) = 1/4
x(x+6) = 8x + 24
x^2 +6x = 8x + 24
x^2 +6x - 8x - 24 = 0
x^2 - 2x - 24 = 0
x^2 - 6 x + 4x - 24 = 0
x ( x - 6 ) + 4 ( x -6 ) = 0
( x - 6 ) ( x + 4) = 0
( x - 6 ) = 0 or ( x + 4) = 0
x = 6 or x = -4
days never negative so x = -4 not possible
so , x = 6 days
p takes 6 days
and q takes 6+6 = 12 days
so p's work in a day = 1/x
q requires x+6 days
so q's work in a day = 1/x+6
now
1/x + 1/x+6 = 1/4
x+6 + x / x(x+6) = 1/4
x(x+6) = 8x + 24
x^2 +6x = 8x + 24
x^2 +6x - 8x - 24 = 0
x^2 - 2x - 24 = 0
x^2 - 6 x + 4x - 24 = 0
x ( x - 6 ) + 4 ( x -6 ) = 0
( x - 6 ) ( x + 4) = 0
( x - 6 ) = 0 or ( x + 4) = 0
x = 6 or x = -4
days never negative so x = -4 not possible
so , x = 6 days
p takes 6 days
and q takes 6+6 = 12 days
Similar questions