Talvar Singh can do
a work in 10 days & that of
Balvindar Singh in 15 days. Balvindar Singh starts
the work alone but after 3 days he left the work &
Talvar Singh join the work. In how many days will
the total work be finished?
Answers
Answered by
3
Step-by-step explanation:
total work. effeciency
talvar. 10. 3
30
balvinder 15. 2
for 3 days, balvinder did 3×2=6
remaining work = 30-6= 24
talvar days = 24/3 = 8
total days = 3+8 = 11 days.