Team of 5 skilled workers can build a wall in 20 days; 8 semi-skilled workers can build the same wall in 25 days; 10 unskilled workers can build the same wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall

Answers

Answered by bondacreation2347
0

Answer:

Step-by-step explanation:

41 days