Technical) Exam. 27.02.2011)
3. A particular job can be completed
by a team of 10 men in 12 days.
The same job can be completed
by a team of 10 women in 6 days.
How many days are needed to
complete the job if the two teams
work together?
Answers
Answered by
2
Answer:
According to the question,
10 men’s one day’s work = \frac{1}{12}
∴ 1 man one day’s work = \frac{1}{12\times 10} = \frac{1}{120}
Similarly,
1 woman one day’s work = \frac{1}{6\times 10} = \frac{1}{60}
∴ (1 man + 1 woman)’s one day’s work = \frac{1}{120}+\frac{1}{60}
= \frac{1+2}{120} = \frac{3}{120} = \frac{1}{40}
∴ (10 man + 10 woman)’s one day’s work = \frac{10}{40} = \frac{1}{4}
Therefore, both the team can finish the whole work in 4 days.