Ten men can complete work in 9 days. Three days after they started the work, 2 men joined. In how many days will all of them together complete the remaining work?
Plz give the step by step solution
Answers
Answered by
0
Step-by-step explanation:
let no of days for 8 men and 2 other men be x and y
10×9=8×x=2×y
=>x=45/4,y=45
8 men in 45/4 days=1work
8 men 1 day=4/45
8 men after 3 days =4/15
work left = 11/15
10 men in 1 day =1/9
10 men in 'a' day = 11/15
=>a/9= 11/15
=>a=33/5=6.6 days
They will complete it in 6.6 days