Ten men can finish construction of a well
in eight days. How many men are needed
to finish the work in half-a-day?
(1) 160 men
(2) 120 men
(3) 100 men
(4) 80 men
Answers
Answered by
2
Answer:
1 is the answer of the question
Answered by
0
160 men will be needed for complete construction of well in half day