Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?

Answers

Answered by sushma34
5
10 - 4
8 - ?

8*4/10
32/10
=3.2

3.2 is ur answer
Hope it helps u
Bye

Anonymous: i think it's wrong
Answered by Anonymous
5
Hey


10 men takes 4 days to complete a task .


1 man will take 4* 10 days to complete same task .


So ,


8 men will take 4 * 10 / 8 days to complete same task .


= 4 * 10 / 8


= 10 / 2


= 5 days .


Concept used :-


One man takes more time to complete a work rather less time .



thanks :)