Ten men take 4 days to complete the task of tarring a road.How many days would 8 men take
Answers
Answered by
5
10 men take = 4 days
1 man take =
0.4 days
so, 8 men will take =
3.2 days
Answered by
1
Work Done = number of men * number of days
Work Done = 10(4) = 40 man days
When 8 men are working then, days required are ‘d’.
Work Done = 40 = 8d i.e. d = 5 days