Ten men working 6 hours a day to completa a
Work in 18 days. How many hours a day must
15 man work to complete in 12 days ??
Answers
Answered by
1
Step-by-step explanation:
Description for Correct answer:
10men×6hr×18days1 work=15men×H hr/day×12days1 work
=6 hrs/day
Similar questions
Social Sciences,
6 months ago
Hindi,
6 months ago
Social Sciences,
6 months ago
Physics,
1 year ago
History,
1 year ago
English,
1 year ago