Ten men working 6hours a day take 12days to complete a job. How long will it take 8men working 12hours a day to complete the same job :^.^​

Answers

Answered by kv44489
1

Answer:

let the day be x

then, (10×6×12)/(8×12×x)

720/96x

x = 720÷48/96÷48 (48 as HCF)

x= 15/2

x= 7 1/2 days

I hope it's help you.

|| keep learning ||

Answered by TaniyaArmy
3

Answer:

this is the answer to your question