Ten men working 6hours a day take 12days to complete a job. How long will it take 8men working 12hours a day to complete the same job :^.^
Answers
Answered by
1
Answer:
let the day be x
then, (10×6×12)/(8×12×x)
720/96x
x = 720÷48/96÷48 (48 as HCF)
x= 15/2
x= 7 1/2 days
I hope it's help you.