Ten men working for 6 day's can complete 5 copies of a book. If there are 8 men working to complete 4 copies of the book , how many days will it take ?
Answers
Step-by-step explanation:
10 men working for 6 days can complete =5 copies of the book
total men's labour= 10×6 = 60
60 ÷ 5= 12 men's labour
total no. of copies=4
12×4 = 48
total men=8
48÷8 = 6
☆ so , 8 men will take 6 days to complete 4 copies of book
If there are 8 men working to complete 4 copies of the book, it will take 9.375 days.
Given:
10 men working for 6 days can complete
5 copies of a book
To find :
8 men working to complete 4 copies of the book, how many days will it take
Solution :
The number of copies filled by 10 members in 1 day is 1/6
work done by 10 numbers on one book is 1/5
If 8 men work for 4 copies in x days then
work done on one book per day is
But work done on one book by one person is the same
So,
x=9.375 days
Thus, it will take 9.375 days.