ten men working for 6 days for 10 hours each, finish 5/21 of a peace of work. how many men working at the same rate for the same number of hours each day, will be required to complete the remaining work in 8 days
Answers
Work do one = 5/21
Remaining work = 1- (5/2) = 16/21
5/21 of a work can be done in 6 days working
10 hours a day by = 10 m
1 work can be done in 6 days working 10 hours a day by = (10 × 21)/5
1 work can be done in 1 day working 10 hours day by = (10 × 21 × 6)/5 men
16/21 work can be done in 8 days working 10 hours a day by = (10 × 21 × 6 × 16)/(5 × 21 × 8) = 24 men
Answer:
24
Step-by-step explanation:
Lets first find the number of working hours required to complete 5/21 of the work.
M = number of men
D = number of days
H = number of hours worked per day
N = work done
MDH = N
10 x 6 x 10 = 5/21
Let the total number of hours required to complete the work be x then
x = 5/21 / 600
x = 600 x 21/5
x = 2520 hrs
So, the remaining work is 16/21 x
=16/21 x 2520
= 1920 hrs req. to complete remaining work
Now, MDH = N = 1920
M X 8 X 10 = 1920
M = 1920 / 80
M = 24
Hope it helps...