Ten women can complete a work in seven days and 10 children take 14 days to complete the work. How many days will five women and 10 children take to complete the work?
Answers
Answered by
2
Answer:
10 Women = 7 Days
10 Children = 14 Days
5 Women is 1/2 of 10 Women, so half the days
5 Women = 7/2 = 3.5 Days
5 Women + 10 Children = 3.5 + 14 = 17.5 Days.
Thus, It would take 5 Women and 10 Children 17.5 Days to complete the Work.