Prabesh can finish a piece of work in 15 days. He worked for 10 days and left. How much is the remaining part of the work to be finished?

❎NO SPAM❎

Answers

Answered by siddhartharao77
12

Given that Prabesh cah finish a work in 15 days.

Work done by prabesh in 1-day = (1/15).

Given that he worked for 10 days and left.

⇒ (1/15) * 10

⇒ 2/3.


Remaining work = 1 - 2/3

                           = 1/3.



Hope this helps!

Answered by Ashishkumar098
10
Answer :-

_______________________

Given:-

Prabesh can finish a piece of work in 15 days.

And he worked for 10 days and left the work.


To find :-

After 10 days how much is the remaining part of the work to be finished.


Salutation :-


Let , the whole work be 1.

If in 15 days Pradesh finishs 1

Then in 1 days Pradesh finishs 1 / 15

And in 10 days Pradesh finishs 10 / 15 = 2 / 3

So , Pradesh worked in 10 days 2 / 3

Now , work remaining

= 1 - 2 / 3

= ( 3 - 2 ) / 3

= 1 / 3. [ ★ Required answer ]