To do a certain work, A and B work on altemate days with B beginning the work on the first day. A alone the same work in 24 days. If the work gets completed in 11 days, then B alone can complete th part of the original can complete work.
Answers
Answered by
10
Step-by-step explanation:
given :
- certain work of A and B = 24 days
- complete work = 11 days
to find :
- original can complete work = ?
- original can complete work = ?
solution :
A work for one day = 1/48
B work for one day = 1/9
- = 1/9 + 6 days for complete for B
we take the B complete work = a
- 8/9 = 6/a
- = 27/4
days 4 time complete certain work
- = 4×27/4
orginal part to completed = 27 days
Answered by
6
- .Let the efficiency of A be 1 unit
- Total work = 48 x 1 = 48 units
- Working alternatively,
- Time for which A work in days = days
- Work done by A = units
- Time for which B work = 6 days
- Work done by B = 48 - = units
- Efficiency of B = 128/18 units per day
- Time taken by B to finish 4 times the work = 192/(128/18) = 27 days
Hope it helpful for you
Similar questions