Math, asked by Ameena012, 2 months ago


 \huge \sf{ \overline {\underline{ \underbrace\red{ |question| }}}}
If 14 typists typing 6 hours a day can take 12 days to complete the manuscript of a book , then how many days will 4 typists , working 7 hours a day , can take to do the same job ?



  \huge\red{answer \: needed \: with \: full \: explanation}

Answers

Answered by ItzMissLegend
6

 \huge\blue{Answer}

36

Step-by-step explanation:

Given that 14 Typists = 6 hours 12 days

4 Typists = 7 hours x days

It will take 36 days to complete the same job.

Answered by MrImpeccable
4

ANSWER:

Given:

  • 14 typists type 6hrs a day and take 12 days to complete a work.

To Find:

  • No. of days will 4 typists, working 7 hours a day take to complete the same work.

Solution:

\text{We are given that}\\\\:\implies\text{14 typists $\xrightarrow{Working}$ 6 hours $\xrightarrow{Take}$ 12 days}\\\\\text{Total Work Done:}\\\\:\implies14\times6\times12- - - -(1)\\\\\text{Let the days required in the other case be x. So,}\\\\:\implies\text{4 typists $\xrightarrow{Working}$ 7 hours $\xrightarrow{Take}$ x days}\\\\\text{Hence, Total Work Done:}\\\\:\implies4\times7\times x- - - -(2)\\\\\text{We know that, the Work Done is same. Hence,}\\\\\text{From (1) and (2),}

\\\\:\implies4\times7\times x=14\times6\times12\\\\\text{Transposing 4$\times$7 to RHS,}\\\\:\implies x=\dfrac{14\!\!\!\!/^{\:\,2}\times6\times12\!\!\!\!/^{\:\,3}}{4\!\!\!/\times7\!\!\!/}\\\\:\implies x=2\times6\times3\\\\\bf{:\implies x=36}\\\\\text{\bf{Hence, the days required to complete the work is 36 days.}}