A contractor can complete a certain piece of work, with certain number of men, in 9 days. But 6 of them remained absent from the very first day, so the rest could finish the work in 15 days. How many men were originally employed ?
1-12
2-15
3-18
4-24
Answers
Answered by
5
Answer:
Given :-
- A contractor can complete a certain piece of work, with certain number of men, in 9 days.
- But 6 of them remained absent from the very first day, so the rest could finish the work in 15 days.
To Find :-
- How many men were originally employed.
Solution :-
Let,
According to the question :
By doing cross multiplication we get,
Hence, the men were originally employed is :
The men were originally employed is 15 .
Hence, the correct options is option no (2) 15 .
▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃▃
Answered by
3
Step-by-step explanation:
Let there be x men at the begining less men, more days
∴ 15:9::x:(x−6) ⇒ 15(x−6)=9x
⇒ 6x=90 ⇒ x=15
or
Let the contractor employed 'x' men to complete the task in 9 days.
So, TOTAL WORK = (9x) Mandays
But, 6 out of x men were absent and the remaining completed the work in 15 days.
Thus, TOTAL WORK = 15(x-6) Mandays
So, 9×x=15×(x−6)
=>6×x=90
=>x = 15 Men (Answer)
Similar questions