________________
"A" and "B" can complete a piece of work 24 days & 36 days respectively .
They start the work but, three(3) days before completion of work , "A" left .
How many days will the total work be completed ?
__________________
Give Answer , Without spam .✌✌
Answers
Given :-
- A can complete work in 24 days .
- B can complete work in 36 days.
- A left work 3 days before it's completion .
To find :-
- Number of days in which the entire work will be completed.
Solution :-
We are provided with the capacity of both workers A and B that they can complete the work alone in how many days.
Firstly we'll find the working capicity of each worker in a single day .
→ A can complete work = 24 days
→ In one day A can complete part of work =
→ B can complete work = 36 days
→ In one day B can complete part of work =
Now we'll find how much units of work has to be completed ( Total work units ) .
By Finding the LCM of working capacity of each worker .
→ Total work = LCM of 24 and 36 is 72.
→ So total units of work is 72.
Now we'll find that each worker can complete how many units of work in every single day.
→ A can complete units of work =
→ A can complete 3 units per day .
→ B can complete Units of work =
→ So B can complete 2 units per day .
As its given that A left the work 3 days before it's completion .
Then we can say that the work that A will complete if he stays 3 days more now will be completed by B .
→ Work completed by A in 3 days = 3×3
→ So 9 units are added in the total work units .
→ Total work = 72 + 9 = 81 .
→ Work done by (A+B) = Total work units/Total units of work done by both workers per Day.
→ Work done by A+B =
→ Work done =
Hence the work will be completed in 16.2 days
Step-by-step explanation:
We are provided with the capacity of both workers A and B that they can complete the work alone in how many days.
Firstly we'll find the working capicity of each worker in a single day .
→ A can complete work = 24 days
→ In one day A can complete part of work =
→ B can complete work = 36 days
→ In one day B can complete part of work =
Now we'll find how much units of work has to be completed ( Total work units ) .
By Finding the LCM of working capacity of each worker .
→ Total work = LCM of 24 and 36 is 72.
→ So total units of work is 72.
Now we'll find that each worker can complete how many units of work in every single day.
→ A can complete units of work = 3
→ A can complete 3 units per day .
→ B can complete Units of work = 2
→ So B can complete 2 units per day .
As its given that A left the work 3 days before it's completion .
Then we can say that the work that A will complete if he stays 3 days more now will be completed by B .
→ Work completed by A in 3 days = 3×3
→ So 9 units are added in the total work units .
→ Total work = 72 + 9 = 81 .
→ Work done by (A+B) = Total work units/Total units of work done by both workers per Day.
→ Work done by A+B = 81 / 3+2
→ Work done = 16.2
HOPE IT HELPS YOU OUT
PLS MARK AS BRAINLIEST ANSWER
FOLLOW ME TOO FOR MORE ANSWERS