the certain number of pages need to be typed. a, b and c are assigned to do this job. however, c leaves after 4 days when 40% of the job was complete. in this way, it takes 13 days to finish the job. also b can type twice as fast
Answers
Answered by
2
Complete question should be-
How much would the fastest worker take to type the entire set of pages alone?
Answer-
A and B take 9 days to complete the remaining 100-40=60% of the job.
Therefore, in one day A and B can complete – 60/9=20/3% of the job
Since A is twice as slow as B, A completes 1/3 of job.
Hence, A can finish= 20/3 × 1/3 = 20/9% of the job in a day ....(1)
Since B is twice as fast as A, B completes 2/3 of job.
Hence, B can finish = 20/3 × 2/3 = 40/9% of the job in a day ....(2)
In the first 4 days. A and B would have finished = 20/3 × 4= 80/3% of the job
Therefore, C would have finished = 40-80/3 = 40/3% of the job in 4 days
So, C can finis h = 40/3 ÷ 4 = 10/3% of the job ....(3)
Hence, B is the fastest among the three workers.
Now B will take 9/40 × 100 days = 22.5 days.
Fastest worker will take 22.5 days to complete the job.
Thanks for asking...
How much would the fastest worker take to type the entire set of pages alone?
Answer-
A and B take 9 days to complete the remaining 100-40=60% of the job.
Therefore, in one day A and B can complete – 60/9=20/3% of the job
Since A is twice as slow as B, A completes 1/3 of job.
Hence, A can finish= 20/3 × 1/3 = 20/9% of the job in a day ....(1)
Since B is twice as fast as A, B completes 2/3 of job.
Hence, B can finish = 20/3 × 2/3 = 40/9% of the job in a day ....(2)
In the first 4 days. A and B would have finished = 20/3 × 4= 80/3% of the job
Therefore, C would have finished = 40-80/3 = 40/3% of the job in 4 days
So, C can finis h = 40/3 ÷ 4 = 10/3% of the job ....(3)
Hence, B is the fastest among the three workers.
Now B will take 9/40 × 100 days = 22.5 days.
Fastest worker will take 22.5 days to complete the job.
Thanks for asking...
Similar questions