The construction of a new basketball court in Anil's school was to be completed in
10 weeks 2 days, 3 weeks 4 days have passed since the construction started. How much
more time is left ?
Answers
Answered by
28
Answer:
Left Time = (10w,2D) - (3w,4D) = 6w, 5D (Ans)
(Mark as brainlist)