The cost baseline is developed during which process?40
Answers
Answered by
0
Project Management
The cost baseline is developed during which process?

Abdel Fattah Ibrahim
CDT Director - Colgate Palmolive
Views (2516) Followers (2) Upvote (3)
Follow Upvote Comments
Register to Answer this Question
Register
Log in if you're already a Bayt.com member.
View Related Questions
1 Answers
Top Voted First Newest First Oldest First

by Jahabar Sadiq Ifthikar Procurement and Tendering Specialist - 3 years ago
The Cost Performance Baseline is an “authorized time-phased budget-at-completion (BAC) used to measure, monitor, and control overall cost performance on the project” (PMI’s fourth edition PMBOK®). All the minor budgets are added together to create the overall Cost Performance Baseline, which is displayed as a graph of cumulative funds to be spent over time. The periods of time are on the x-axis and the funds are on the y-axis. The periods of time could be days, months, years, etc. Because spending is generally less at the beginning and end of the project, the line on the graph representing cumulative funds tends to be in an S-shaped curve.
The cost baseline is developed during which process?

Abdel Fattah Ibrahim
CDT Director - Colgate Palmolive
Views (2516) Followers (2) Upvote (3)
Follow Upvote Comments
Register to Answer this Question
Register
Log in if you're already a Bayt.com member.
View Related Questions
1 Answers
Top Voted First Newest First Oldest First

by Jahabar Sadiq Ifthikar Procurement and Tendering Specialist - 3 years ago
The Cost Performance Baseline is an “authorized time-phased budget-at-completion (BAC) used to measure, monitor, and control overall cost performance on the project” (PMI’s fourth edition PMBOK®). All the minor budgets are added together to create the overall Cost Performance Baseline, which is displayed as a graph of cumulative funds to be spent over time. The periods of time are on the x-axis and the funds are on the y-axis. The periods of time could be days, months, years, etc. Because spending is generally less at the beginning and end of the project, the line on the graph representing cumulative funds tends to be in an S-shaped curve.