The cost of leveling the square plot of side 50 m at the rate of
4 per square meter is _________
a) 500
b) 10000
c) 400
d) 600

Answers

Answered by kshrijagupta58
1

Answer:

Area of plot = Side*Side

                   = 50*50

                   = 2500 m^{2}

Cost of leveling = Area*Cost

                        =  2500*4

                        = 10000 (b)