The estimated production of an organization is 5,00,000 units. The standard man hours required to produce each unit is 5 hours. The past experiences show that the workability of each employee in man hours is 2,000 hours per year. How many workers are required to produce estimated units?
Answers
Answered by
1
Answer:
500000÷400
=1250 Workers
PLEASE MARK AS BRAINLIEST
Answered by
0
Answer:
[1:39 pm, 25/12/2021] @@Shatakshigupta: or example
Annual Production of the company: 5,00,000 units
Standard Manhours required per unit: 2 hours
Planned Manhours for the year (5,00,000 * 2)= 10,00,000 hours
Annual Contribution of a worker = 2000 hours
No. of workers required (10,00,000/2000) = 500
500000÷400
=1250 Workers