The estimated production of an organization is 5,00,000 units. The standard man hours required to produce each unit is 5 hours. The past experiences show that the workability of each employee in man hours is 2,000 hours per year. How many workers are required to produce estimated units?​

Answers

Answered by arorarajkumar91
1

Answer:

500000÷400

=1250 Workers

PLEASE MARK AS BRAINLIEST

Answered by guptashatakshi9801
0

Answer:

[1:39 pm, 25/12/2021] @@Shatakshigupta: or example

Annual Production of the company: 5,00,000 units

Standard Manhours required per unit: 2 hours

Planned Manhours for the year (5,00,000 * 2)= 10,00,000 hours

Annual Contribution of a worker = 2000 hours

No. of workers required (10,00,000/2000) = 500

500000÷400

=1250 Workers

Explanation: