The first step in project crashing is
Answers
Answered by
9
Answer:
The first step is to identify which are the tasks that if we shorten them, we will also shorten the project completion. These tasks are those that are included in the critical path. Apply the CPM (Critical Path Method) to calculate the critical path and identify which are those critical tasks.
Explanation:
Mark me as Brainlyst answer...........
Answered by
1
Answer:
The first step is to identify which are the tasks that if we shorten them, we will also shorten the project completion. These tasks are those that are included in the critical path. Apply the CPM (Critical Path Method) to calculate the critical path and identify which are those critical tasks.