Accountancy, asked by rkd55, 2 months ago

The following particulars are available is respect to a contract as on 01.01.2010:

a. Contract price: ₹50,000

b. Total cost of contract up to date: ₹32,000

c. Cost of uncertified work: ₹1,280

d. Cash received: ₹25,000

Calculate the cost of certified work.

Answer:

A. ₹30,620

B. ₹31,720

C. ₹30,720

D.₹30,820​

Answers

Answered by amiteshsalui
1

Answer:

c

Explanation:

mark me as brainliset

it's a request

very please

Similar questions