Business Studies, asked by hiteshrobby, 8 months ago

The foreman in the welding department wanted to know what value of allowance to use for a particular section of the shop. A work sampling study was authorized. Only two activity categories were considered: (1) welding and other productive work, (2) personal time, rest breaks and delays. Over a four-week period, where there are 40 hours per week, 191 observations are made at random times. Each observation captured the category of activity of each of 10 welders in the shop section of interest. Results indicated that category 2 constituted 28 % of the total observations. (a) Can you conclude that realized PFD is 28 % in the factory at 100*(1-0.05) % confidence level with 8% precision? (b) If a total of 74 work units were produced during the 4 weeks, and all category 1 activity was devoted to producing these units, what was the average time spent on each unit?

Answers

Answered by asritadevi2emailcom
16

Explanation:

random times. Each observation captured the category of activity of each of 10 welders in the shop section of interest. Results indicated that category 2 constituted 28 % of the total observations. (a) Can you conclude that realized PFD is 28 % in the factory at 100*(1-0.05) % confidence level with 8% precision? (b) If a total of 74 work units were produced during the 4 weeks, and all category 1 activity was devoted to producing these units, what was the average time spent on each unit?

Similar questions