The group that authorises changes that must be installed faster than the normal process is called the:

Answers

Answered by Shashank7739584746
1

Answer:

Emergency Change Advisory Board(ECAB)

Explanation:

ECAB committee support the change management team in cause any priar changes are required in urgency. They assist in handling any emergency changes to process the change manager, so as to avoid any undesirable delays.