Science, asked by kapoorrohan626, 9 months ago

the image represent the network diagram of a company X
what will be the earliest possible time for the completion of project?​

Attachments:

Answers

Answered by Shepherdbutt20
0

Answer:

Explanation:

We took nodes 6 and 6l as one and the same. Instead, we can retain

them as different nodes. Then, in order to provide connectivity to the

network, we join nodes 6l and 6 by a dummy activity