The Indian government launched a Pilot Scheme for procurement of aggregate power of __________ on a competitive basis for three years under medium term from commissioned power plants.
A.2500 MW
B.1800 MW
C.2000 MW
D.1500 Mw

Answers

Answered by reemabiswas2004
0
The right answer is A. 2500 MW.
Answered by GhaintMunda45
0

Hey !

______________________________

The Indian government launched a Pilot Scheme for procurement of aggregate power of 1500 Mw on a competitive basis for three years under medium term from commissioned power plants.