The maximum demand of a power plant is 40 mw. The capacity factor is 0.5 and the utilization factor is 0.8. Find the load factor.
Answers
Answered by
3
MD = 40 MW
Capacity factor 0.5
Utilization factor = 0.8
= 0.625
PLZZZ MARK AS BRAINLIEST
Capacity factor 0.5
Utilization factor = 0.8
= 0.625
PLZZZ MARK AS BRAINLIEST
Answered by
0
Answer:
The maximum demand of a power plant is 40MW.The capacity factor is 0.5 and the utilization factor is 0.8. Find plant capacity