Math, asked by sugaarmy1651, 9 days ago

The number of days (d) required to build a mall varies jointly with the floor area (a) and the number of stories (s),and inversely with the number of workers (w),if 120 men can build a two story mall with a floor area of 300m² in 30 days, how long will it take 400 men to build a 5 story mall with an area of 1080m²

Answers

Answered by shiwkishor
0

Step-by-step explanation:

Let it will take d days

=> d/30=(5×1080×120)/(2×300×400)

= (600×1080)/(600×400)

=>d=(1080×30)/400 = 81 days.