• The objective of project crashing is to
Answer
A. revise the network critical path and completion times when the schedule falls hopelessly behind
B. minimize the cost of crashing
C. the amount of unused resources for an activity.
D. the amount of time an activity can be delayed without delaying the entire project.
Answers
Answered by
0
Answer:
The aim of crashing is to achieve the maximum decrease in schedule for minimum additional cost. This can be done by: Addressing productivity issues being experienced by the current resources and trying to find ways of increasing their efficiency. Increasing the assignment of resources on critical path activities.