The Product Owner determines how many product backlog items Development team selects for a sprint. true or false

Answers

Answered by Anonymous
0

Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult for the Development Team to determine what it should work on.

True

Answered by lovingheart
3

Answer:

Its false.

Explanation:

Not only product owner but it’s a collaboration between a product owner and development team and they decide which product should be selected for the sprint. Development team can be able to recognize the best quality of the product. After selecting the products they will discuss it with product owner for the final decision. Therefore, there is mutual understanding between product owner and development team that take final decision.