Math, asked by sonalikandari987, 2 months ago

The project manager of Good public relations gathered the data shown in Table 2.11 for a new advertising campaign.
1. How long is the project likely to take?
2. What is the probability that the project will take more than 38 weeks?
3. Consider the path A-E-G-H-J. What is the probability that this path will exceed the expected project duration?

Attachments:

Answers

Answered by priyaag2102
2

Good public relations Gathered Data information

Step-by-step explanation:

a) The critical path is A-E-F-H-J.

The expected time for each activity is:

A: (8 + 4*10 + 12) / 6 = 10

E: (8 + 4*10 + 12) / 6 = 10

F: (5 + 4*6 + 7) / 6 = 6

H: (2 + 4*5 + 8) / 6 = 5

J: (4 + 4*5 + 8) / 6 = 5.3333

The expected time to completion is then 10 + 10 + 6 + 5 + 5.3333 = 36.3333 weeks

b) The variance for the tasks on the critical path are:

A: [(12 - 8)/6]² = 0.4444

E: [(12 - 8)/6]² = 0.4444

F: [(7 - 5)/6]² = 0.1111

H: [(8 - 2)/6]² = 1.0000

J: [(8 - 4)/6]² = 0.4444

The total variance for the critical path is 0.4444 + 0.4444 + 0.1111 + 1.0000 + 0.4444 = 2.4444

The standard variation is √2.4444 = 1.5635

The z-score corresponding to a completion time of 38 weeks is:

z = (38 - 36.3333) / 1.5635 = 1.0660

P(z > 1.0660) = 0.1432

The probability that the project will take more than 38 weeks is 0.1432.

c) The expected time for activity G is:

G: (1 + 4*3 + 5)/6 = 3

The expected time for path A-E-G-H-J is 10 + 10 + 3 + 5 + 5.3333 = 33.3333

The variance for task G is:

G: [(5 - 1)/6]² = 0.4444

The total variance for the path A-E-G-H-J is 0.4444 + 0.4444 + 0.4444 + 1.0000 + 0.4444 = 2.7776

The standard deviation for the path is √2.7776 = 1.6666

The z-score corresponding to a completion time of 38 weeks is:

z = (38 - 33.3333) / 1.6666 = 2.8001

P(z > 2.8001) = 0.0026

The probability that path A-E-G-H-J will take more than 38 weeks to complete is 0.0026

Similar questions