The rates of working of Aand B are in ratio 3:4 . the number of days taken by them to finish the work are in ratio
Answers
Answered by
7
Answer:
Given :The rates of working of A and B are in the ratio 3:4.
To Find : The number of days taken by them to finish the work are in the ratio
Solution:
The rates of working of A and B are in the ratio 3:4.
Efficiency is inversely proportional to the time
So, the ratio of time of A and B is
So, the ratio of time of A and B is 4:3
Hence The number of days taken by them to finish the work are in the ratio 4:3
Answered by
1
Answer:
4:3 is the answer..