The road adjacent to badminton court at Central
University, Lucknow, needed repair. So, the university
authorities hired Parikh to do the job. Parikh selected a
certain number of workers and assured the university
that work will be done in 10 days. Unfortunately, 4
workers were absent from the beginning and the task
took 50 days to complete. Can you tell us how many
workers Parikh hired initially.
Answers
Answered by
9
Answer: 5
Step-by-step explanation:
Given,
Let x workers complete the work in 10 days.
But, 4 workers were absent from the beginning.
∴ (x - 4) workers completed the work in 50 days.
⇒ x * 10 = (x - 4 )* 50
⇒ x = 5x - 20
⇒ 4x = 20
∴ x = 5
∴ Parikh initially hired 5 workers .